How to Test an Ignition 8.3 Upgrade Before It Reaches the Line
Replay one production shift in a test environment. Compare work orders, downtime and shift totals across Ignition, Sepasoft MES and the systems people use to make decisions.

Trace one shift before you change a version
A production dashboard can look healthy after an upgrade while the operator and production planner are working from different records. Imagine a short stop at 05:58, a restart at 06:03 and a work order that closes at 06:10. Where does the stop land in the shift report? If the database connection drops during that period, who confirms that the missing events came back?
Pick a line where you can answer those questions today. Sit with the operator at handover and follow one work order from the planning system to dispatch, through the stop and restart, and into the end-of-shift report. Bring a planner or supervisor into the review. Save the inputs, the current outputs and any exceptions people already correct by hand. That becomes your baseline.
Write down the versions along that path
For each handoff, record the Gateway version, which Sepasoft modules and connectors are installed, the database destination and any report or integration that reads historical tag paths. Inductive Automation recommends testing in a development or test environment before upgrading production. Its 8.3 guide describes historical path changes for the Core Historian and documents where legacy SQL Historian syntax still applies. Identify the historian your plant actually uses before deciding which queries to retest. [1]
Check the proposed Gateway and MES module combination against Sepasoft's Downloads page. Keep that compatibility decision with the inventory and use the vendor's documentation for the installation order. If you run multiple Gateways, map which one sends data, which one stores it and what versions the two will run during the change. [2]
Replay the shift and reconcile the outputs
Run the baseline inputs through an isolated, representative test environment. Start with the normal shift. Then interrupt a test database connection, reconnect it and make the same operator correction your team would make on the floor. For a data path that uses Store and Forward, check where events go after the connection returns. A queue draining is only one observation. Compare the delivered events and report totals with the baseline before accepting the result. [3]
Agree on the tolerances with the people who own the numbers. Work-order and lot identifiers generally need exact matches. Decide what time tolerance, if any, makes sense for an event near a shift cutoff. Have an operator and the person who uses the totals independently check their own views.
| Case | Evidence to keep | Who signs off |
|---|---|---|
| Normal work order | Matching order and lot identifiers from dispatch to the production record | Planning and production |
| Stop across shift change | Stop and restart timestamps, reason code and allocation to each shift | Shift supervisor |
| Database interruption | Recovered event list and reconciled totals with gaps or duplicates accounted for | Controls or IT and production |
| Operator correction | Corrected reason visible in the report with a traceable change | Operator and report owner |
Decide how to stop and recover
Protect the recovery window before booking the production change. Inductive Automation recommends taking a Gateway backup before upgrading. Rehearse restoring the pre-upgrade Gateway and separately check what your team must restore or reconcile at external databases and interfaces. Record who makes the stop decision, how supervisors will see the state of the line and how people will account for events recorded during the change. [1]
If a discrepancy changes a production decision or moves downtime to the wrong shift, hold the rollout. Find the first handoff where the records disagree and repeat the replay after correcting it. Once the line passes, have the same owners reconcile the first live shift. That is a practical point to decide whether the next line is ready for the same change.