A Packing Station Passed at the Supplier. Can It Take the First Live Order?
Use a site acceptance test to check what happens when a packed carton and its production record stop moving together.

One sealed carton, no confirmed posting
At 7:10 on a hypothetical factory's first commissioning shift, the new packing station seals a carton from a training order. Its screen says the cycle is complete. The dispatch screen has no matching packed quantity. The carton is physically ready to move, but the operator cannot tell whether it was never recorded or whether the posting is late.
The supervisor has a specific decision to make: release this station for the first live order or keep the agreed previous process. A video of a carton clearing the supplier's conveyor cannot answer it. The deciding evidence is what the operator and dispatch can see in the installed workflow, including what they can do when confirmation is missing.
Keep the supplier results and name the open question
Take the supplier's acceptance report and mark the checks that still apply, such as the agreed carton range or sequence of functions. Open the site test sheet alongside it. List the actual order input, label source, destination record and person authorized to release the cell to production. Assign any items the supplier could not show at its own premises before the installation team leaves.
The International Society of Automation's published summary of ANSI/ISA-62381-2026 and IEC 62381:2024 distinguishes factory, site and integration acceptance testing for process-industry automation. It is a useful distinction here, not a claim that the standard applies to this packaging station. Quindart's requirements template discusses stating what cannot be demonstrated before installation. [1] [2]
A rehearsal with a carton that cannot be confirmed
In a test environment agreed with the site team and integrator, run a training order using a representative carton and the agreed site data paths. Simulate a missing posting confirmation through the test interface. Do not bypass guards or interfere with live controls. Keep the carton identified and apart until the production and dispatch records can be reconciled. Ask the supervisor to observe the actual indications instead of narrating the expected answer.
| Test moment | What to observe | Who owns the next step |
|---|---|---|
| Normal carton | Dispatch sees the right carton and quantity exactly once | Operator and dispatch lead compare the two records. |
| Confirmation missing | The carton stays identifiable and is not sent as dispatch-ready | Supervisor follows the agreed hold or fallback. |
| Posting reconciled | The original carton is matched and no second quantity is created | The integration owner reconciles it with dispatch. |
Sign for a process the next shift can run
Ask the next shift's lead, without the supplier explaining the screen, to show where an unconfirmed carton goes and who clears it. Keep the site's signed result with the actual carton identifier and the observed destination-state record. A pass means the team can run the normal handoff and handle the exception without losing or duplicating a carton in the records.
If they cannot, state which condition is open and who will retest it. Use the agreed previous process if it remains suitable and authorized. The supervisor can then make the release decision from evidence, not from the fact that the equipment has already arrived.