What You Can Sign Off in a Virtual Walkthrough and What Needs Shop-Floor Proof
A walkthrough shows layout, reach, access and operator position well. It cannot show how a wrong lot, a late part or a rework job moves through the cell. Here is a sorting test and a 12-item sign-off table for one cell.

A model shows where things are. It does not carry your Tuesday.
The sorting test
Integrators now let customers see an automation project before the machine exists. Eclipse Automation announced a public preview of RealitySync on iPhone, iPad and Apple Vision Pro on October 15. It describes the app as a way to experience a project before and during the build. [1]
Eclipse has also discussed how immersive technology can support design reviews, training, equipment installation and factory simulation. That is useful to an owner. The open question is what your signature should mean after a walkthrough. [2]
Here is a test you can apply to any item. Ask whether a wrong assumption would be visible from outside the machine in a model. If it would, sign it off in the walkthrough. If it only appears when real orders, lots or exceptions arrive, require a recorded shop-floor test. A model shows where things are. It does not carry your Tuesday.
The test fits how design freeze works. Eclipse's guide on choosing a partner before design freeze lists decisions that engineering, operations, quality and finance must lock first. Geometry decisions can be locked in a walkthrough. Decisions about behaviour under real work need proof. [3]
One cell, one wrong lot
Take a hypothetical 55-person shop that machines aluminum housings. It is buying a cell that deburrs, inspects and packs them. All numbers below are illustrative. A typical lot is 48 housings. Revision D moves a mounting boss a few millimetres from revision C, and both revisions are in the building.
In the headset, everything looks right. The robot reaches the infeed tray and the pack bin. The operator can see the inspection camera. The forklift can reach the pallet position. The owner approves the layout, and that approval is sound.
Now follow one real order. The planner releases a job for revision D. The ERP prints a traveller. The machinist attaches a label, but the label template still shows revision C because nobody updated it. Meanwhile the supplier's gasket for 12 of the 48 parts is late, so the lot is split. Quality pulls 6 parts for rework, and they come back to the cell two hours later on a separate tag.
None of this appears in the model. The cell has to decide which program applies, what to do with a partial lot, and where reworked parts go. People upstream have to decide whether the cell's count matches the order. Those decisions sit across the office record, the label, the operator and the cell logic.
If the cell trusts the label, it runs revision C on revision D parts. If the office record only learns the count at the end of the shift, the partial lot looks like a shortage. A walkthrough cannot expose either failure, because nothing is wrong with the geometry.
Sign off in the walkthrough
These six items for the housing cell pass the sorting test. A wrong assumption would show in the model if someone looked for it. The key is to look with the right people, not only with the project sponsor.
| Item | Why a model can show it | What to keep on file |
|---|---|---|
| 1. Cell footprint and aisle clearance | Size and position show against the floor plan. | Dated, dimensioned saved view with the revision of the layout. |
| 2. Robot reach to every pick and place point | The reach envelope is visible from outside. | Reach check per point, including the tallest and smallest housing. |
| 3. Operator position and sightline | A person-height view shows what the operator can see and reach. | Walkthrough with the actual operator and a list of requested changes. |
| 4. Placement of guard doors, light curtains and stops | Position and access are visible. The safety function is not. | Marked-up view. The safety function is verified separately. |
| 5. Forklift and cart access for material | Paths and turning space are visible. | Swept path view using your real cart and pallet sizes. |
| 6. Maintenance access to cabinets, filters and motors | Door swing and clearance are visible. | View signed by the person who will do the maintenance. |
Require a recorded shop-floor test
These six items fail the sorting test. They only appear when real work arrives, so the evidence must be a recorded run on the floor, with your parts, your paperwork and your people. The quantities in the table are illustrative.
| Item | Why a model cannot show it | Recorded evidence to require |
|---|---|---|
| 7. Wrong revision label on a lot | Depends on the data the cell reads and trusts. | Run a revision C label on a revision D lot. The cell must stop and say why. |
| 8. Late supplier part and split lot | Depends on how the office record and floor count a partial lot. | Run 36 of 48 parts, then the remaining 12. Show both counts match the order. |
| 9. Rework job re-entering the cell | The rework path exists in procedure, not geometry. | Run 6 reworked parts on a separate tag. Show they are identified and tracked. |
| 10. Count and status returned to the office record | Depends on the handoff to the ERP or spreadsheet. | Show the planner the order status updating from the cell during a live run. |
| 11. Operator recovery from a stop | Depends on messages, habits and who is nearby. | Operator, not integrator, recovers from three induced faults, timed on video. |
| 12. Cycle time on a real lot | A model uses nominal parts. Real parts vary. | Timed full lot of 48 real housings with every stoppage logged and explained. |
Who decides, and what happens to exceptions
Split the signature by role. Operations and the operator sign off items 2, 3, 5 and 6, because they are the people who live with reach, sightline and access. Engineering signs item 1 and confirms that item 4 is followed by a separate safety verification. Finance should not accept a milestone payment tied to items 7 to 12 on the strength of a headset session.
For items 7 to 12, name one person on your side who decides pass or fail before the test. Agree the pass criteria in writing. Agree what happens on a failure: a fix and a rerun, a documented workaround with an owner, or a change to the office process. Many of these failures are not machine faults. A stale label template is an office record problem, and no amount of cell programming fixes it.
If the integrator proposes to simulate an exception instead of running it, ask what data the simulation assumes. A simulated wrong lot that already knows it is wrong proves nothing about how your label reaches the cell.
A test for next week and the evidence to request
Next week, take the sign-off list from your current or planned project and mark each item with one question: would a wrong assumption be visible from outside the machine in a model? Items that fail go on a separate list headed recorded shop-floor test. Bring both lists to the next design review and ask the integrator to confirm the sort.
Before final acceptance, request the following. Video of each test in items 7 to 12, with the lot, revision and order number visible. The paperwork used in each run, including the traveller and tag. A log showing what the office record said before and after each run. A written list of faults induced during recovery and the time to clear each. The names of the people who ran them, including at least one of your operators.
Quindart treats the walkthrough as one input to observing floor reality early. The order, lot and exception evidence still has to come from the floor.